THERMAL INSULATION MORTARS

PERTHERM ADH

Adhesive for Thermal Insulation Sheets

DESCRIPTION

The product is a cement-based product containing mineral aggregates of a special particle size and chemical additives improving product performance, that is used for bonding polystyrene thermal insulation sheets (EPS, XPS, ROCKWOOL)

It conforms to TS EN 13566 of June 2013.

TECHNICAL SPECIFICATIONS

Appearance Grey
Mixing Ratio 6-7 lt water /25 kg
Amount of Consumption 4-5 k/m2 (depending upon application type)
Application Temperature +5 oC to +35 oC
Time for Use 40-60 minutes
Vessel Life 3 hours
Toxicity Non-toxic
Splice Strength >0.5 N/mm2
Bending Strength  2 N/ mm2  Min.
Pressure Strength   6 N/ mm2  Min.
Water Absorption  Max. 5 gr for 30 min.  - Max. 10 gr for 240 min.
*    The above values are valid for + 23oC and 50% relative humidity. The time is shortened at high temperatures and extended at low temperatures.

AREAS OF USE

It is used for bonding heat insulation sheets on interior and exterior walls (e.g. gross concrete, brick, cement-based plaster, and gas concrete) in buildings.

BENEFITS

It is easy to prepare and apply. It gives proper working time. It does not lead to drift at vertical applications. It has high adhesion properties. It is resistant to freeze-thaw cycling.

INSTRUCTIONS FOR USE

Before starting the application process, the surface should be free from foreign materials and slightly wetted. 25 kg of EKOKAT PERTHERM ADH should be mixed with 5.5-6.0 liters (e.g. 22-24%) of clean water with the help of a low revolving mixer or a trowel until a homogeneous consistency is achieved. The mixture should be allowed to rest for 5-10 minutes and then mixed for another 1-2 minutes. The prepared mortar should be consumed within 2 hours. The prepared mortar should be applied with a width of at least 5 cm in the form of lumps in the middle such that it would surround the insulation plate. The heat insulation sheets are laid out from top to bottom. After the adhesive has dried, the dowels are placed in the center of the panel and all joints. No space should be left between the sheets to the extent possible, and the fine spaces should be filled with a heat insulation tape or foam. Adhesion process should be completed within 20 to 25 minutes. Do not apply above 35 ° C or below + 5 ° C. The plaster should be applied on the bonded insulation sheets after 2 days. These values ​​are valid for a surface and ambient temperature of 20oC. The time is shortened at high temperatures and extended at low temperatures.

PACKAGING

25 kg PE reinforced craft bags
64 shrink bags on one palette (110x110 cm).

STORAGE CONDITIONS AND SHELF LIFE

No more than two palettes should be placed on top of each other in their unopened original packaging, in a cool and dry environment. Shelf life is 12 months from date of production under suitable storage conditions.

SAFETY MEASURES

Work clothes, protective gloves, goggles and masks suitable for workers health and safety should be used during the application. Due to irritant effects of uncured material, it should be washed with plenty of water and soap immediately in case of contact with skin and eyes. If swallowed, seek medical advice immediately. No food and drink should be brought into application areas. Store it out of reach of children. Please refer to the safety data sheet for further information.

RESPONSIBILITY

Our Company may not be held liable for any application errors that might be suffered if the product is not used for its intended purposes, or if it is failed to conform to the conditions and proposals specified above regarding technical application. This technical data sheet contains information that is current as of the date of issuance hereof. The manufacturer hereby reserves its right to change this data sheet at any time.

  • EK 3001.010.25
  • Grey
PERTHERM ADH
CONSUMPTION CALCULATOR
Application Thickness (mm)
Area ( m2 )